IETEL OS · Pass 5 vertical slice 7
Mobilization Readiness — IET-2026-0043
Whether IETEL is actually ready to begin execution — consuming the approved Plan and Baseline without re-asking any of it.
Live workspace — changes save to the shared IETEL OS database through the real, authorized API, visible to everyone assigned to this project. You need to be signed in as the Position this step requires; the server decides that, never this page.
INTERNAL ONLY
Approved Plan Reference
Inherited from Project Planning — not re-entered here.
Inherited- Planned start
- 2026-10-05
- Planned completion
- 2026-10-16
- Permitting needs (from Plan)
- Local fire marshal review required for warehouse door hardware change before finalizing — already flagged as a design exception; confirm inspection scheduled before Week 1 ends.
- Procurement needs (from Plan)
- Cloud-based access control panel, electrified exit device conversion kit (2), PoE network switch — all standard stock items, no long-lead procurement expected.
- Crew needs (from Plan)
- One Lead Technician + one Field Technician for the two-week window. No specialty licensed trade needed in-house — dedicated circuit work is already scoped to the licensed-electrician subcontractor line in the Estimate, not IETEL crew.
INTERNAL ONLY
Mobilization Readiness
Source: project-mobilization Process & Project Mobilization Checklist SOP — every prerequisite must be satisfied; a project is never started partially ready.
Derived