Change Management — IET-2026-0043
A condition in the field conflicts with the Approved Design — documented, priced, and approved before anything changes, never applied silently.
Prototype UI — changes are saved to this browser only (no backend, no shared/multi-user storage). Reloading the page keeps your changes; clearing browser storage resets it to the sample data.
Current Baseline
Derived, not stored — the highest-numbered approved Design Snapshot and Estimate Revision for this Assessment. The originally authorized baseline (Project Creation, Contract) never changes; this is what the project should be built to right now.
Derived- Current Design Snapshot
- #2 — IET-ASMT-2026-001-DESIGN-SNAP-2
- Supersedes
- IET-ASMT-2026-001-DESIGN-SNAP-1
- Current Estimate Revision
- #2 — IET-ASMT-2026-001-EST-REV-2
- Supersedes
- IET-ASMT-2026-001-EST-REV-1
The originally authorized Contract baseline stays Snapshot 1 / Revision 1 — a Change Order amends it, it never rewrites what was sold.
Change Orders
Source: change-management Process & Change Order Standard.
Inherited- What changed
- Add battery backup (UPS) for the access control panel so it continues logging and operating during a power outage.
- Reason / origin
- Customer request
- Reported by
- Project Manager
- Reported
- 2026-10-07
- Scope impact
- Add one UPS unit sized for the access control panel load, wired between the building circuit and the panel.
- Technical design impact
- Power architecture stays dedicated-supervised; adds a UPS stage. No change to network, cybersecurity, opening decisions, or Acceptance Criteria.
- Schedule impact
- 1 day
- Materials cost impact
- $650.00
- Labor cost impact
- $120.00
- Subcontractor cost impact
- $0.00
- Project price impact
- $1,116.50
- Customer authorization required
- Yes
Operations Manager Decision
- Decided by
- Operations Manager
- Decided
- 2026-10-07
- Note
- Straightforward addition — no risk to the Week 2 close-out schedule beyond the stated one day. Approved.
Customer Authorization
- Status
- Authorized
- Decided
- 2026-10-07
- Note
- Customer facilities contact approved the UPS addition and the $1,116.50 price impact by email the same day it was priced.
- Resulting Design Snapshot
- #2 — IET-ASMT-2026-001-DESIGN-SNAP-2
- Resulting Estimate Revision
- #2 — IET-ASMT-2026-001-EST-REV-2
- What changed
- Add a second 8-port PoE switch to support two additional camera drops the customer flagged during the Week 1 walk-through.
- Reason / origin
- Customer request
- Reported by
- Project Manager
- Reported
- 2026-08-19
- Scope impact
- Add a second 8-port PoE network switch alongside the existing unit, same rack location.
- Technical design impact
- Schedule impact
- 0 days
- Materials cost impact
- $240.00
- Labor cost impact
- $60.00
- Subcontractor cost impact
- $0.00
- Project price impact
- $435.00
- Customer authorization required
- Yes
Report a New Change
A new field discovery or customer request — reported, then priced, then routed for Operations Manager approval, matching change-management's own four steps exactly.